Construction

Secure your Project Management

Ligne 15 Sud OA Centre

Contracting authority: SOCIETE GRAND PARIS

Prime contractor: SYSTRA

Company of realization : GROUPE FAYAT (Urbaine de Travaux – Satelec – Darras et Jouanin)

Place: Val de Marne

Description:

The project consists of carrying out the construction work for all trades on 7 ancillary structures located between the Créteil l’Echat station and the Villejuif Louis Aragon station of the Grand Paris Express line 15 South.

MESLI Consulting has been mandated by the FAYAT group (Urbaine de Travaux, Satelec, Darras et Jouanin) to carry out the OPC mission (Ordering, Control, and Coordination) by elaborating the planning of the studies, purchases, and works under PRIMAVERA as well as the follow-up of the progress, and more particularly for the study and work phases. 

Ligne 15 Sud

Contracting authority: SOCIETE GRAND PARIS

Prime contractor: EGIS – SETEC

Company of realization : SDEL – ALISE

Place: Ile de France

Description :

The project consists of carrying out HV-LV and fiber optic work on the entire Line 15 South, which runs from the Noisy-Champs station to the Pont de Sèvres station. The 33 kilometers of the line include 16 stations, 38 ancillary works, and 2 maintenance sites for the rolling stock.

MESLI Consulting is assisting the client in updating the work objectives with the support of detailed planning from the study phase to the commissioning of the line under Primavera P6 and monitoring the progress of the project.

GARE SAINT-DENIS PLEYEL

SAINT-DENIS PLEYEL STATION

ClientSOCIETE DU GRAND PARIS

Project manager : BESIX

Location : SAINT-DENIS (FRANCE)

Description : Support to the client in the tender phase for the formalization of the station planning in TCE and the launch of the planning of studies, purchases, and works in accordance with the contractual commitments defined by the contracting authority.. The tool used is Primavera P6, writing of the summary note.

Accompaniment of the client in the meetings with the project manager. A risk analysis was conducted based on pre-mitigation and post mitigation scenarios to verify the consistency of the contractual milestones using Primavera Risk Analysis. The tender was successfully received by the project owner.

accompagnement gestion de projet, primavera formation, Solution Oracle Aconex, cabinet conseil management projet, cabinet de conseil en financement de projet, cabinet de conseil en gestion de projet, cabinet de conseil spécialisé en management de projet, cabinet de gestion de projet, Analyse de retards projet, audit et diagnostic planning, conseil en gestion de projet, consultant gestion de projet, contract management, coordinateur de projet, coordination de projets, déployer un planning de référence, expert gestion de projet, expertise gestion de projet, claims expert management, claims management, formation contract manager, formation gestion contractuelle, Formation Claims Management, Formation gestion de contrat FIDIC, formation gestion des contrats, Formation gestion des risques, formation management de projet, formation ms project, formation opc, formation planification de projet, Formation Planification TCE, formation primavera, formation primavera p6, Formation sensibilisation à la gestion des contrats, gestion contractuelle, gestion de projet de construction, gestion de projet industriel, gestion de projet planification, gestion des réclamations clients, Gestion des contrats FIDIC, gestion des contrats, gestion des risques et incertitudes, gestion des risques, gestion du changement, gestion des risques et opportunités, mesli consulting, Gestion des risques projet, gestion d'un projet de construction, interface gestion de projet, Management de projet, Primavera risk analysis simulation de monte carlo, mission opc, mission opc chantier, opc batiment, opc chantier, Pilotage et suivi de projet, pilotage projet, planification de projet, Primavera simulation de monte carlo, risques et incertitudes, Solution Primavera P6, Oracle Primavera Cloud, Deltek Acumen Fuse & risk, formation gestion de contrat, réclamation client et fournisseur, simulation de monte carlo, solution gestion de projet, suivi de projets, Consultant contract management, gestion de projet primavera, primavera p6, Gestion de contrat, formation contract management, OPC mission planning, contrôle de projets, contrôle et suivi des projets, PMO, Consultant PMO, Bureau de gestion de projets, Gouvernance de projet PMO, Standards de gestion de projet méthodologies, Outils de PMO, Méthodologies de projet, Alignement stratégique, Reporting de projet, Gestion des risques de projet, Formation en gestion de projet, Optimisation des processus de projet, Management de portefeuille de projets, Amélioration continue en gestion de projet.

TOUR AXA (PARIS, LA DÉFENSE)

AXA TOWER (LA DÉFENSE)

Contracting authority: COGEDIM

Prime contractor: BOUYGUES

Place: Paris (La Défense)

Description: the AXA tower becomes the CB31 tower and gains 66 m to culminate at 225 m instead of the current 159 m. The CB31 tower project consists of extending the building in a spiral. The CB31 tower is about to surpass the Montparnasse tower to become the highest skyscraper in France.

MESLI CONSULTING was contacted by BOUYGUES Construction for our project planning service. Due to the large number of actors, MESLI CONSULTING was also responsible for the management of the main project interfaces.

KING ABDULLAH UNIVERSITY OF SCIENCE AND TECHNOLOGY

Contracting authority: The Kingdom of Saudi Arabia

Prime contractor: OGER International

Place: Djeddah (Saudi Arabia)

Description: the construction of KAUST (King Abdullah University of Science and Technology), including 64 housing buildings, 7 civic buildings (Yacht Club, gallery, bank, library, theater, waste treatment plant), villas, 21 research buildings, the oceanic research center (Morc), a mosque, a fire station, a clinic, a service station, a supermarket, a golf club, a tennis club, schools, office buildings and other facilities for a total surface area of 630 000 m2.

MESLI CONSULTING was contacted by Oger International for our expertise in project management, notably for our project planning experience with PRIMAVERA for more than 20 buildings, the production of progress reports, monitoring the subcontractors’ plans, and the compilation of the master plan.

MESLI CONSULTING was also responsible for all the planners and participated in key decisions for the project.